United KingdomCase Law
Take-or-pay needs no prior proof of gas availability
Availability language is not a condition precedent to an 80% take-or-pay charge; shortfalls are handled as deductions, proofs need no special-damages pleading, and appeal costs follow the event.
By Taxxa AI OyPublished 25 November 2026
Industry: Across industries
A take-or-pay buyer must pay for 80% of the annual contract quantity
Nationalarchives even though the seller has not first proved it made the full quantity available for delivery, where the contract deals with shortfalls through deductions rather than through an availability threshold
Nationalarchives.
The gas supply contracts required the seller to deliver and the buyer
Nationalarchives, provided gas was available and tendered for delivery, to take and purchase the annual contract quantity
Nationalarchives. The take-or-pay articles then obliged the buyer to pay for any shortfall below 80% of the combined annual quantity across both contracts
Nationalarchives, less gas not taken or delivered for force-majeure reasons or by the seller's act or omission
Nationalarchives, with make-up gas available in later years. Reading the availability proviso in isolation as a condition precedent cuts across that structure: the seller's supply duty was itself only a best-efforts duty tempered by price and force-majeure terms
Nationalarchives, the buyer's duty was already reduced from 100% to 80%
Nationalarchives, and non-availability is expressly handled as a deduction from the quantity charged for
Nationalarchives.
The contract also never defines what proving "availability" would mean — the full daily quantity at each plant every day, 80% averaged over the year, or aggregation of surplus at one plant against deficiency at the other
Nationalarchives — although the take-or-pay charge itself is computed on an aggregated annual basis
Nationalarchives. The absence of any such metric confirms that the parties did not intend an availability condition precedent
Nationalarchives. The seller's admitted shortfalls were instead reflected in the "Cutback" deduction in its calculation
Nationalarchives, which is how the contract prices non-availability
Nationalarchives.
A liquidator assessing such a claim applies proof-of-debt standards, not the pleading standard for special damages
Nationalarchives. Quantum, however large, does not raise the standard of proof as a matter of law
Nationalarchives, though a liquidator may spend longer examining a large claim. A letter setting out a readily comprehensible calculation, identifying the contractual terms and how they operated on the events, and inviting contact for clarification is sufficient to engage the process
Nationalarchives; that is the point at which the liquidator may require further evidence on specific figures such as the cutback, the price or the volumes taken
Nationalarchives. The information is not solely in the creditor's hands
Nationalarchives, since the buyer's records show daily consumption and force-majeure notifications
Nationalarchives, and there was nothing inherently implausible about a key supplier's claim
Nationalarchives.
Once a creditor appeals against rejection of a proof, costs leave the proof regime and follow the event
Nationalarchives. The rule that a creditor bears the cost of proving a debt covers the proof itself, not adversarial court proceedings on appeal from the liquidator's decision
Nationalarchives, with winding-up costs otherwise payable from the company's assets.
On the facts, the supplier's March 2016 invoice
Nationalarchives for US$12,635,661.06
Nationalarchives — a 5,911,973.544 MMBtu deficiency
Nationalarchives for contract year 2015
Nationalarchives priced at US$2.1373 per MMBtu
Nationalarchives after adjusting the combined annual quantity for accepted supply failures
Nationalarchives — should not have been rejected for want of availability evidence
Nationalarchives, and the Court of Appeal's reversal of the first-instance admission of the proof
Nationalarchives was set aside
Nationalarchives with the liquidator's rejection reversed
Nationalarchives and no remittal
Nationalarchives, the moment to dispute the computation having long passed
Nationalarchives.
The legal basis is the Iron and Steel Complex Contract and the Megamod Contract
Nationalarchives (articles 2.1, 2.4, 2.5, 2.7, 2.8, 3.1, 3.3, 14 and 16) with sections 432 and 434 of the Companies Act Chapter 81:01 and Rules 74, 76, 79, 88 and 89 of the Companies Winding Up Rules in its Second Schedule.
When rejecting a large take-or-pay proof, identify the disputed figures and ask for further evidence on them instead of rejecting for want of threshold availability proof.