Two asbestos checklists apply from 1 October 2026
From 1 October 2026, VDI inspectors assess asbestos-work permit applications against a dedicated checklist and complete a safe-work checklist on any inspection where asbestos work is found.
By Taxxa AI OyPublished 9 September 2026
Industry: Construction
Employers planning construction work that exposes workers to asbestos face two new State Labour Inspectorate (VDI) checklists from 1 October 2026E TAR
E TAR
E TAR. The Chief State Labour Inspector's Order No. EV-147 of 9 September 2026
E TAR inserts them into the inspection-checklist Order No. EV-96 as new points 1.32 and 1.33: a checklist for assessing permit applications to carry out construction work while exposed to asbestos
E TAR, and a checklist for controlling the safe performance of such work
E TAR.
The permit checklist is used to assess applications for a leidimas vykdyti statybos darbus veikiant asbestuiE TAR. The safe-work checklist controls safe asbestos removal
E TAR, and inspectors must use it beyond targeted asbestos inspections
E TAR: they complete it during a targeted inspection
E TAR and whenever they encounter asbestos work in the course of any other planned or unplanned inspection, even where the main inspection already uses a different checklist or thematic report
E TAR. A contractor whose site involves asbestos must therefore be ready for the asbestos-specific check on any inspection, not only an asbestos-targeted one
E TAR.
Both checklists apply within a permission-first regime. Before demolition of structures containing asbestos, alteration of such structures, or asbestos removal, an employer prepares a work plan meeting the asbestos rulesE TAR and files it with the VDI territorial department together with the manager's order approving the plan and the notice of asbestos-related activity
E TAR. Where VDI finds documentary defects, it notifies the employer within five working days of receipt and sets a correction period of at least five working days
E TAR; filings left uncorrected are not examined further
E TAR. Employers whose documents and planned worker-protection measures comply are entered in the published register of employers meeting the competence and readiness requirements within one working day of the decision
E TAR, and an employer that does not meet them may not start the demolition, alteration or removal work
E TAR. VDI may also halt asbestos-exposed construction work at a specific workplace, unit or site.
The order also tasks VDI territorial heads with briefing their inspectors, the IT and document-management head with publishing the order and checklists in the Register of Legal Acts, and the budget and planning head with preparing the corresponding thematic reports in the DSS IS monitoring system by 23 September and publishing the updated checklists on the Inovacijų agentūra website.
Legal basis: Order No. EV-147 of 9 September 2026 amending Order No. EV-96 of 4 July 2017E TAR (point 1 in force 1 October 2026
E TAR).
File asbestos-work notices against the correct VDI checklists: use the permit checklist for permit requests and expect the safe-work checklist on any inspection where asbestos work is found.
Sources
- Dėl Lietuvos Respublikos vyriausiojo valstybinio darbo inspektoriaus 2017 m. liepos 4 d. įsakymo Nr. EV-96 „Dėl Ūkio subjektų patikrinimų kontrolinių klausimynų, rinkos priežiūros klausimynų ir teminių ataskaitų patvirtinimo” pakeitimo
- Dėl Lietuvos Respublikos socialinės apsaugos ir darbo ministro ir Lietuvos Respublikos sveikatos apsaugos ministro 2004 m. liepos 16 d. įsakymo Nr. A1-184/V-546 „Dėl Darbo su asbestu nuostatų patvirtinimo“ pakeitimo
- Dėl Kompetencijos ir pasirengimo vykdyti su asbesto poveikiu susijusius statybos darbus vertinimo tvarkos aprašo patvirtinimo