Top court: subcontract penalty pass-through needs contract footing
Riigikohus voided a Tartu ruling in a 23,989-euro works-contract fee fight: courts must test the subcontract's own clauses and foreseeability before passing a 15 000-euro third-party penalty down the chain.
Af Taxxa AI OyOffentliggjort 25. november 2026
Branche: På tværs af brancher
The Civil Chamber has annulled the Tartu Circuit Court's judgment
Riigikohus in a works-contract fee fight and sent the case back
Riigikohus. Estwood OÜ sued Osaühing Arendus & Haldus for an unpaid fee of 23,989 euros
Riigikohus plus interest at 0.02 percent per day
Riigikohus and 1,114.16 euros in damages for pre-litigation legal costs, under a 30 April 2019 works contract
Riigikohus to maintain a third party's power-line corridors under that third party's framework agreement with the defendant
Riigikohus. The county court upheld the fee
Riigikohus but set 15,000 euros of it off against the defendant's damages
Riigikohus — a penalty paid to the third party over false volume records
Riigikohus — and rejected the legal costs
Riigikohus. The circuit court found no breach proven
Riigikohus and awarded a further 15,900 euros plus partial legal costs
Riigikohus. In its judgment of 25 November 2026
Riigikohus in case 2-24-2658
Riigikohus the Chamber annulled the circuit judgment for a material breach of the duty to give reasons
Riigikohus (TsMS § 692 lõike 1 punkt 2, § 669 lõike 1 punkt 5) and remanded to the same circuit court
Riigikohus (TsMS § 691 punkt 2), granting the cassation. No longer disputed on remand is the 23,989-euro fee claim
Riigikohus; open are the set-off and the pre-litigation costs
Riigikohus
Riigikohus.
The case turns on whether the contractor breached a collateral contractual duty — recording actual work volumes in the database
Riigikohus — even though it achieved the contracted result. Collateral duties agreed alongside the main obligation bind the parties under VÕS § 23 lõike 1 and § 8 lõige 2
Riigikohus, with remedies under §§ 100, 101 and 115
Riigikohus. Courts must apply the relevant clauses on the facts before them even when uninvoked (TsMS § 436 lõige 7, § 438 lõige 1)
Riigikohus — but not by surprise: the reading must be flagged and discussed with the parties. Both lower courts overlooked subcontract clause 5.5 on accrediting fractional spans
Riigikohus; the county court held the framework duties extended to the subcontractor
Riigikohus, but the circuit court never assessed whether the framework agreement had become part of the subcontract
Riigikohus. On remand the court must test clause 5.5, including its interplay with clause 5.7 on payment for work actually done (VÕS § 29 lõige 6)
Riigikohus, and whether framework duties bound the subcontractor
Riigikohus.
No established correction practice excused the contractor
Riigikohus: practice under VÕS § 23 lõike 1 punkt 2 and § 25 lõige 1 needs conduct both parties knowingly share
Riigikohus. If breach is found, set-off damages stand where the statutory conditions are met
Riigikohus — with foreseeability under VÕS § 127 lõige 3 decisive
Riigikohus, since the penalty duty arose under the framework agreement
Riigikohus. A subcontractor performing the main contract can foresee penalty exposure from misrecording
Riigikohus, and intent or gross negligence removes the foreseeability cap
Riigikohus. VÕS § 645 lõige 1 on late notice of defects is irrelevant to such collateral-duty damages
Riigikohus.
Pre-litigation legal costs fall under VÕS § 128 lõige 3
Riigikohus: the § 115 lõige 1 conditions must first be met
Riigikohus and the costs must be reasonable in necessity and amount
Riigikohus. Counsel spending may prove unnecessary for fee collection if the set-off succeeds
Riigikohus, so the costs claim travels with the set-off outcome on remand
Riigikohus. The costs of the proceedings themselves stay with the circuit court under TsMS § 173 lõike 3 second sentence
Riigikohus.
Legal basis: Riigikohtu tsiviilkolleegiumi otsus 25.11.2026 asjas 2-24-2658
Riigikohus, applying VÕS §§ 8, 23, 25, 29, 100, 101, 115, 127, 128, 641, 644 and 645 and TsMS §§ 173, 436, 438, 651, 654, 655, 669, 691 and 692.
Subcontractors and main contractors: write volume-reporting and framework pass-through duties expressly into the subcontract, and test penalty pass-through on foreseeability at signing.